Yesterday workers were preparing the ground for
constructing pavements and garden plots around 601C.
Next to Punggol Secondary.
Work on 601C void deck is also in progress.
Repair work on 16 floor should be completed by end of next week
(I was told).
The damaged rooftop has bee reconstructed and
yesterday painters are patching up that side of the wall for
painting.
Now only left the other portion of the side wall
waiting for 16th ceiling repair to finish.
And when that is done painting for
601C is finished.
601D is making good progress, but windows still not installed.
Ext walls painting is just starting for one front row block (nearest to foodcourt).
Seems like workers are trying to finish the front row blocks
internal fittings first. Still, there is is good progress even though
I think these blocks would be 2-3 months behind
601C/D in final completion.