This afternoon the debris and parts of the fallen boom were removed
by a newly erected crane at Block 601B/C.
Block 601C's exterior walls painting is expected to be completed
by end April 2010.
I also saw workers already preparing the window frames to
fit in the window panes at the 3rd level.
Most of the interior fittings are already done. I could
see the tiles on the bathroom walls.
I was informed Block 601C is on schedule for completion in 3rd qtr inspite
of the accident.
After that it is up to HDB to inspect and issue the keys which I was
told is likely to be earliest in September 2010. If there are many
defects, key collection for 601C at worst should be by 1st qtr of 2011.