Punggol.sg Punggol.sg
Punggol.sg Forum Terms of Service
Punggol Surroundings Punggol Topaz Historical Background Submitted Articles Articles - Child Care Centre Birds in My Backyard - Punggol 21
Notice: Crime Prevention Punggol Bus Guide Punggol LRT Guide BBQ Pit Booking
 Completed Project  Project In Progress
 Condominium  Others
Enrichment Programme Essential Telephone Numbers Infant/Child Care Services Kindergarten Primary/Secondary Schools Healthcare Establishments RCs, Fire Post Shopping Mall in/near Punggol Fashion and Accessories Food Country Clubs Camps Places Of Worship Others
July 27, 2024, 04:15:13 AM *
Welcome, Guest. Please login or register.

Login with username, password and session length
News: Terms of Service
 
   Home   Photos Help Calendar Login Register  

Pages: 1 ... 10 11 [12] 13 14 ... 34   Go Down
  Print  
Author Topic: Pictures of work in progress ( HDB BTO Punggol Sails )  (Read 187641 times)
0 Members and 3 Guests are viewing this topic.
tom

Offline Offline





Ignore
« Reply #44 on: July 08, 2011, 08:40:02 AM »

A bird's eye view of the whole Punggol Sails Constructional site and look at it's overall up to date progress.....



* IMGP0947.JPG (163.28 KB, 640x480 - viewed 1262 times.)
Logged


Advertisement



tom

Offline Offline





Ignore
« Reply #45 on: July 08, 2011, 08:49:45 AM »

Closeup view of the whole project.

Compare this photo with the rest of the previous photos taken and you'll notice the difference in total work done to date.....



* IMGP0948.JPG (207.33 KB, 640x480 - viewed 2516 times.)
Logged
tom

Offline Offline





Ignore
« Reply #46 on: July 08, 2011, 09:11:02 AM »

Take a look at individual Block progress .....Block 207B

Three levels of floor completed with casement windows for panels and all prefab units installed.

Concrete floor slab on the 4th level in progress. Photo showed a prefab concrete floor panel being lifted up for installation. ( circle green in colour )



* IMGP1030.JPG (198.14 KB, 640x480 - viewed 2534 times.)
Logged
tom

Offline Offline





Ignore
« Reply #47 on: July 09, 2011, 09:54:30 AM »

Construction Review Block 207A.....

Part of the Block completed Level 5. The other half of the Block was at level 6. On both levels perimeter railings are up as a safety guard.

All completed floors were with front panel walls and casement windows.

Workers are still busy on both levels preparing to uplift prefab components. The main ones are the prefab columns follow by bomb shelters / stores.



* IMGP0949.JPG (209.25 KB, 640x480 - viewed 2508 times.)
Logged
Pages: 1 ... 10 11 [12] 13 14 ... 34   Go Up
  Print  
 
Jump to:  



Powered by MySQL Powered by PHP Powered by SMF 1.1.21 | SMF © 2006, Simple Machines
Simple Audio Video Embedder
Valid XHTML 1.0! Valid CSS!
Page created in 0.097 seconds with 20 queries.
About Punggol.sg Forum | Terms of Service
Hosted on Xssist™ Dedicated Server