Punggol.sg Punggol.sg
Punggol.sg Forum Terms of Service
Punggol Surroundings Punggol Topaz Historical Background Submitted Articles Articles - Child Care Centre Birds in My Backyard - Punggol 21
Notice: Crime Prevention Punggol Bus Guide Punggol LRT Guide BBQ Pit Booking
 Completed Project  Project In Progress
 Condominium  Others
Enrichment Programme Essential Telephone Numbers Infant/Child Care Services Kindergarten Primary/Secondary Schools Healthcare Establishments RCs, Fire Post Shopping Mall in/near Punggol Fashion and Accessories Food Country Clubs Camps Places Of Worship Others
July 27, 2024, 12:24:04 AM *
Welcome, Guest. Please login or register.

Login with username, password and session length
News: Terms of Service
 
   Home   Photos Help Calendar Login Register  

Pages: 1 ... 7 8 [9] 10 11 ... 34   Go Down
  Print  
Author Topic: Pictures of work in progress ( HDB BTO Punggol Sails )  (Read 187617 times)
0 Members and 4 Guests are viewing this topic.
tom

Offline Offline





Ignore
« Reply #32 on: May 06, 2011, 09:09:49 AM »

Block 207D is in between Blocks 208A and 207C happen to be the last to be constructed. The picture is a bit hazy.

At the moment it is still at foundation level. Although most foundations had been concreted, trenches still need to be refilled.

In the next two to three weeks progress should catch up and level of completion should be on par with that of Block 207C . ( based on the progress of other blocks, this estimation should be quite close )



* IMGP9293.JPG (189.45 KB, 640x480 - viewed 2080 times.)

* IMGP9294.JPG (200.76 KB, 640x480 - viewed 2121 times.)
Logged


Advertisement



tom

Offline Offline





Ignore
« Reply #33 on: May 18, 2011, 06:05:27 AM »

A picture taken from Punggol Field ( the main entrance to the Punggol Sails construction site ) .

Normally the first level takes a longer time to build because columns, beams, floor slab had to be fabricated on site.

Each steel reinforcement bar had to be bent, shaped and tie up according to structural drawings. Next carpenters had to work on the formworks, bolted them firmly for concreting. Concrete takes 28 full days to cure before formwork is allowed to be removed.

Once the first level is built, the second level up to the top of the building are mostly using factory built pre-fabricated building components. From past records in Punggol,  3 floors can be put up within a period of 2 months on average.



* IMGP9665.JPG (178.15 KB, 640x480 - viewed 2004 times.)
Logged
tom

Offline Offline





Ignore
« Reply #34 on: May 18, 2011, 06:23:35 AM »

Take a look at Block 208A, pictures taken from under the lrt tracks next to the construction site before heavy rain starts pouring.



* IMGP9679.JPG (174.22 KB, 640x480 - viewed 1994 times.)

* IMGP9678.JPG (192.84 KB, 640x480 - viewed 1915 times.)
Logged
tom

Offline Offline





Ignore
« Reply #35 on: May 25, 2011, 10:30:36 AM »

Today although the sky is cloudy ( going to rain soon with thunder and lighting flashes ) but the atmosphere is quite clear.

Photos taken shows a better contrast. A bird-eye view of Sails showing all the seven blocks of flats.





* IMGP9870.JPG (213.43 KB, 640x480 - viewed 1773 times.)
Logged
Pages: 1 ... 7 8 [9] 10 11 ... 34   Go Up
  Print  
 
Jump to:  



Powered by MySQL Powered by PHP Powered by SMF 1.1.21 | SMF © 2006, Simple Machines
Simple Audio Video Embedder
Valid XHTML 1.0! Valid CSS!
Page created in 0.158 seconds with 20 queries.
About Punggol.sg Forum | Terms of Service
Hosted on Xssist™ Dedicated Server