At the moment it will generally take about 2 to 3 months before completion of bore piling works. So daily you can see mobile concrete mixers moving in and out of the construction site, supplying freshly mixed concrete for the piling systems.
Once piling completes, the next stage will be the digging of trenches for foundations. We'll then see carpenters working in groups, fabricating formworks. Steel benders preparing reinforcements and footings for overhead tower cranes will be constructed.
Soon overhead tower cranes will go up and then the building site will be buzzing with activities. We will then report, review and update construction progress, the faster it goes, the more we'll keep readers informed of what's happening.