Completion date for
601D is now
by end of Sept 2010 (MyHDBpage).
Lets wait and see what the other block's completion
dates would be, especially for
601C. Expecting a surprise?
I think so

For those of you who are worried about painting progress
particularly
602C - my advice is
DONT WORRY
TOO MUCH ABOUT IT. For example, if it
does not rain
continously for
1 week - the painting could be finished in
10 days .
Because I can see Kay Lim have arranged 3 to 4 gondolas
of painters, which means literally every side of the walls is being painted at
the same time!

Painting is the least technical work, even you and I can do it

And all the Visdta's blocks' internal fittings and other engrg works are done
and nothing outstanding except the windows (1 week can intall these)
Like Kay Lim stated at site - Vista's construction completion
is in 3rd quarter (latest is sept).