Punggol.sg Punggol.sg
Punggol.sg Forum Terms of Service
Punggol Surroundings Punggol Topaz Historical Background Submitted Articles Articles - Child Care Centre Birds in My Backyard - Punggol 21
Notice: Crime Prevention Punggol Bus Guide Punggol LRT Guide BBQ Pit Booking
 Completed Project  Project In Progress
 Condominium  Others
Enrichment Programme Essential Telephone Numbers Infant/Child Care Services Kindergarten Primary/Secondary Schools Healthcare Establishments RCs, Fire Post Shopping Mall in/near Punggol Fashion and Accessories Food Country Clubs Camps Places Of Worship Others
April 19, 2024, 11:16:32 PM *
Welcome, Guest. Please login or register.

Login with username, password and session length
News: Terms of Service
 
   Home   Photos Help Calendar Login Register  

Pages: 1 ... 3 4 [5] 6 7 ... 24   Go Down
  Print  
Author Topic: Punggol Spectra ( work in progress )  (Read 142894 times)
0 Members and 1 Guest are viewing this topic.
tom

Offline Offline





Ignore
« Reply #16 on: September 09, 2010, 09:13:04 AM »

Have a look at Block 623 A

A bird's eye view of  Block 623 A, showing completed construction of up to the fourth floor level. Most of the prefab units are installed, except for the facade window units.

Probably in the next few days as soon as the window units are delivered, lifting and installation may begin.

From past reports, the speed of installation is about two floors for each month.



* IMGP4079.JPG (203.49 KB, 640x480 - viewed 1584 times.)
« Last Edit: September 09, 2010, 09:14:37 AM by tom » Logged


Advertisement



tom

Offline Offline





Ignore
« Reply #17 on: September 09, 2010, 09:17:05 AM »

A close-up of Block 623 A



* IMGP4075.JPG (212.25 KB, 640x480 - viewed 1524 times.)
Logged
tom

Offline Offline





Ignore
« Reply #18 on: September 09, 2010, 09:54:38 AM »

Block 622 A

A perspective view showing the progress of Block 622 A. First floor completed.

Normally, the first floor takes a longer time to complete because all the columns are cast-in-situ / cast at site for maximum strength, meaning :-

1. Every single column has to be constructed at site. The fabrication of all the vertical high tensile steel bars had to be erected one by one. The horizontal steel bars had to be bent, tie by steel wires, in accordance to engineering drawings.

2. Next the carpenters will come along and instal all pre-fabricated formworks, supported and braced by steel struts.

3. Finally, the columns will be concreted by 1:2:4 concrete mix or accordine to specifications after inspection.

After that comes the pre-fab floor slabs.

So far for Block 622 A, first floor completed, second floor pre-cast floor slabs are in placed.



* IMGP4023.JPG (246.81 KB, 640x480 - viewed 1456 times.)

* IMGP4024.JPG (215.25 KB, 640x480 - viewed 1437 times.)
Logged
tom

Offline Offline





Ignore
« Reply #19 on: September 09, 2010, 10:03:06 AM »

A bird's eye view of Block 622 A.



* IMGP4088.JPG (239.16 KB, 640x480 - viewed 1460 times.)
Logged
Pages: 1 ... 3 4 [5] 6 7 ... 24   Go Up
  Print  
 
Jump to:  



Powered by MySQL Powered by PHP Powered by SMF 1.1.21 | SMF © 2006, Simple Machines
Simple Audio Video Embedder
Valid XHTML 1.0! Valid CSS!
Page created in 0.097 seconds with 21 queries.
About Punggol.sg Forum | Terms of Service
Hosted on Xssist™ Dedicated Server