Punggol.sg Punggol.sg
Punggol.sg Forum Terms of Service
Punggol Surroundings Punggol Topaz Historical Background Submitted Articles Articles - Child Care Centre Birds in My Backyard - Punggol 21
Notice: Crime Prevention Punggol Bus Guide Punggol LRT Guide BBQ Pit Booking
 Completed Project  Project In Progress
 Condominium  Others
Enrichment Programme Essential Telephone Numbers Infant/Child Care Services Kindergarten Primary/Secondary Schools Healthcare Establishments RCs, Fire Post Shopping Mall in/near Punggol Fashion and Accessories Food Country Clubs Camps Places Of Worship Others
April 24, 2024, 10:04:13 PM *
Welcome, Guest. Please login or register.

Login with username, password and session length
News: Terms of Service
 
   Home   Photos Help Calendar Login Register  

Pages: 1 ... 25 26 [27] 28 29 ... 143   Go Down
  Print  
Author Topic: First Executive Condo ( EC ) in Punggol Central.  (Read 703542 times)
0 Members and 3 Guests are viewing this topic.
tom

Offline Offline





Ignore
« Reply #104 on: May 30, 2011, 04:09:53 AM »

Few days ago it was mentioned that there was not much activities happening at Block 31 plot.

Today excavators were still working to recover more r.c. piles. Surprisingly the over head tower crane ( tc4 ) was also installed.

Meaning, the foundation for tc4 had been concreted some time back. Not shown on photo, probably it was covered with sand / mud.



* IMGP0081.JPG (206.99 KB, 640x480 - viewed 3675 times.)

* IMGP0082.JPG (219.68 KB, 640x480 - viewed 3658 times.)

* IMGP0083.JPG (210.73 KB, 640x480 - viewed 3665 times.)

* IMGP0105.JPG (216.72 KB, 640x480 - viewed 3630 times.)
Logged


Advertisement



tom

Offline Offline





Ignore
« Reply #105 on: May 30, 2011, 04:35:43 AM »

Photo shown the location of Tower Cranes on site.

Numbers tc1, tc2, tc3.

Tower crane tc4 ammended to tc6 to follow the numbering system on site.

At the moment there is tc1, tc2, tc3, new tc4 and tc6.

 Smiley will there be a tc5 in between tc4 and tc6 ?



* IMGP9617.JPG (238.5 KB, 640x480 - viewed 3579 times.)
Logged
tom

Offline Offline





Ignore
« Reply #106 on: May 30, 2011, 09:19:12 AM »

Take a look at the installation of formworks by the carpenters working on Block 35.

At the same time once the formwork for the structural beams are completed, steel benders will start to lay steel reinforcements.

Sequence of concreting :-

Columns had to be concreted first.

After proper curing time allow for the concrete, next will be concreting of the beams.

Finally concreting for the floor slab.



* IMGP0089.JPG (216.4 KB, 640x480 - viewed 3481 times.)

* IMGP0090.JPG (221.02 KB, 640x480 - viewed 3500 times.)

* IMGP0122.JPG (209.11 KB, 640x480 - viewed 3302 times.)

* IMGP0123.JPG (211.47 KB, 640x480 - viewed 3301 times.)
Logged
tom

Offline Offline





Ignore
« Reply #107 on: June 03, 2011, 11:53:37 AM »

A bird-eye view of whats happening @ Block 37 Plot taken on May 30th 2011....





* IMGP0099.JPG (239.2 KB, 640x480 - viewed 3012 times.)
« Last Edit: June 03, 2011, 11:56:07 AM by tom » Logged
Pages: 1 ... 25 26 [27] 28 29 ... 143   Go Up
  Print  
 
Jump to:  



Powered by MySQL Powered by PHP Powered by SMF 1.1.21 | SMF © 2006, Simple Machines
Simple Audio Video Embedder
Valid XHTML 1.0! Valid CSS!
Page created in 0.082 seconds with 21 queries.
About Punggol.sg Forum | Terms of Service
Hosted on Xssist™ Dedicated Server