Punggol.sg Punggol.sg
Punggol.sg Forum Terms of Service
Punggol Surroundings Punggol Topaz Historical Background Submitted Articles Articles - Child Care Centre Birds in My Backyard - Punggol 21
Notice: Crime Prevention Punggol Bus Guide Punggol LRT Guide BBQ Pit Booking
 Completed Project  Project In Progress
 Condominium  Others
Enrichment Programme Essential Telephone Numbers Infant/Child Care Services Kindergarten Primary/Secondary Schools Healthcare Establishments RCs, Fire Post Shopping Mall in/near Punggol Fashion and Accessories Food Country Clubs Camps Places Of Worship Others
March 28, 2024, 02:48:39 PM *
Welcome, Guest. Please login or register.

Login with username, password and session length
News: Terms of Service
 
   Home   Photos Help Calendar Login Register  

Pages: 1 ... 11 12 [13] 14 15 ... 143   Go Down
  Print  
Author Topic: First Executive Condo ( EC ) in Punggol Central.  (Read 699877 times)
0 Members and 2 Guests are viewing this topic.
tom

Offline Offline





Ignore
« Reply #48 on: February 27, 2011, 10:34:14 AM »

Recovered piles......

Sequence :

First, the tractor / excavator moves in, dig to remove the top soil around concrete piles.
Second, when the concrete piles were exposed, care has to be taken not to damage the concrete.
Third, excavation to continue to the require depth accordine to drawings / specs / instructions.





* IMGP7716.JPG (243.93 KB, 640x480 - viewed 1414 times.)
Logged


Advertisement



tom

Offline Offline





Ignore
« Reply #49 on: February 27, 2011, 10:47:53 AM »

Pile trimming....

Excessive concrete piles had to be trimmed / cut to the required height.

Close-up view ..


 




* IMGP7697.JPG (226.27 KB, 640x480 - viewed 1461 times.)
Logged
tom

Offline Offline





Ignore
« Reply #50 on: February 28, 2011, 07:28:34 AM »

Formwork completed......

Sequence :

1. Trimming of concrete pile and steel reinforcements.
2. Extension of steel reinforcements for columns.
3. Fabrication of formwork for concreting.

Before concreting, Structural Engineers has to inspect the steel bar reinforcements to make sure it is fabricated in accordance to structural drawings and specifications.



* IMGP7690.JPG (249.29 KB, 640x480 - viewed 1407 times.)
Logged
tom

Offline Offline





Ignore
« Reply #51 on: February 28, 2011, 07:42:09 AM »

Close-up view of formwork, extension of steel reinforcement bars for column and worker cleaning steelwork for Structural Engineer's inpection.

Once inspected, approved, the foundation will be concreted.



* IMGP7709.JPG (215.6 KB, 640x480 - viewed 1413 times.)
Logged
Pages: 1 ... 11 12 [13] 14 15 ... 143   Go Up
  Print  
 
Jump to:  



Powered by MySQL Powered by PHP Powered by SMF 1.1.21 | SMF © 2006, Simple Machines
Simple Audio Video Embedder
Valid XHTML 1.0! Valid CSS!
Page created in 0.15 seconds with 21 queries.
About Punggol.sg Forum | Terms of Service
Hosted on Xssist™ Dedicated Server