Punggol.sg Punggol.sg
Punggol.sg Forum Terms of Service
Punggol Surroundings Punggol Topaz Historical Background Submitted Articles Articles - Child Care Centre Birds in My Backyard - Punggol 21
Notice: Crime Prevention Punggol Bus Guide Punggol LRT Guide BBQ Pit Booking
 Completed Project  Project In Progress
 Condominium  Others
Enrichment Programme Essential Telephone Numbers Infant/Child Care Services Kindergarten Primary/Secondary Schools Healthcare Establishments RCs, Fire Post Shopping Mall in/near Punggol Fashion and Accessories Food Country Clubs Camps Places Of Worship Others
March 29, 2024, 08:43:19 AM *
Welcome, Guest. Please login or register.

Login with username, password and session length
News: Terms of Service
 
   Home   Photos Help Calendar Login Register  

Pages: 1 ... 72 73 [74] 75 76 ... 143   Go Down
  Print  
Author Topic: First Executive Condo ( EC ) in Punggol Central.  (Read 699954 times)
0 Members and 2 Guests are viewing this topic.
tom

Offline Offline





Ignore
« Reply #292 on: January 22, 2012, 07:36:53 AM »

Progress of Block 35 Tower 7 dated 9th January 2012. Completion up to level 12 with most of the prefab components lifted up and strutted on level 13.

Today 22nd January, Lunar New Year Eve, 13 working days later, level 13 completed. Quite a high percentage of prefab components were in place at level 14.

At the moment workers were on leave celebrating Lunar New Year.

Three more floors to go before Block 35 Tower 7 of Prive hit the roof top.



* P1220132.JPG (300.95 KB, 640x480 - viewed 2433 times.)
Logged


Advertisement



tom

Offline Offline





Ignore
« Reply #293 on: January 22, 2012, 08:28:54 AM »

Progress of Block 35 Tower 6 dated 9th January 2012. Completion up to level 12. No prefab components on level 13.

Today 22nd January, Lunar New Year Eve, 13 working days later, level 13 completed. So far no prefab components are found on level 14.



* P1220154.JPG (289 KB, 640x480 - viewed 2319 times.)
Logged
tom

Offline Offline





Ignore
« Reply #294 on: January 22, 2012, 11:57:07 AM »

Block 31 Tower 2 completed up to level 3 on 9th January 2012 with floor slabs laid for the 4th level. No prefab components at floor level.

The latest picture taken on 22nd January 2012 showed an additional floor being built. Now at level 4 with no prefab components on 5th level.



* P1220182.JPG (291.23 KB, 640x480 - viewed 2289 times.)

* P1220191.JPG (299.44 KB, 640x480 - viewed 2312 times.)
Logged
tom

Offline Offline





Ignore
« Reply #295 on: January 24, 2012, 12:40:05 AM »

Today is the second day of Lunar New Year, no activities at site, the earliest Prive reopens for work probably will be on the fourth day of Lunar New Year.

Lets go round the site to capture some Perspective and Elevational views.

 


* P1240358.JPG (286.46 KB, 640x480 - viewed 2174 times.)

* P1240359.JPG (286.18 KB, 640x480 - viewed 2264 times.)
« Last Edit: January 24, 2012, 12:49:56 AM by tom » Logged
Pages: 1 ... 72 73 [74] 75 76 ... 143   Go Up
  Print  
 
Jump to:  



Powered by MySQL Powered by PHP Powered by SMF 1.1.21 | SMF © 2006, Simple Machines
Simple Audio Video Embedder
Valid XHTML 1.0! Valid CSS!
Page created in 0.221 seconds with 21 queries.
About Punggol.sg Forum | Terms of Service
Hosted on Xssist™ Dedicated Server