Block 37 is gradually catching up with Block 35.
At the time when these pictures were taken, men and machine were working closely lifting up prefab panels for installation at Block 37.
Lifting, strutting, securing and alignment of each panel took approximately 30 to 40 minutes only. Only 4 or 5 workers including supervisor are on the job. ( excluding crane driver and riggers at the Basement )
Hi Tom I stumbled onto this forum and noted your updates and pictures for the priveans. It is awesome! Thank you very much. Please keep us posted. Btw my block is 33. Thanks again and grateful to you for all your efforts.